However, contractual breaches, the lack of price updates, and differences between the parties caused successive delays that led to the halt of the work.
So far, approximately USD 1.8 billion has been executed between both dams, while completing the complex would require another USD 4 billion in investment.
The priority will be the Jorge Cepernic dam, previously known as La Barrancosa, which has a 46% progress. The plant will have three turbines and an installed capacity of 360 megawatts (MW), with an estimated generation of 1,860 GWh for the Argentine Interconnection System (SADI). Its completion is scheduled for 2030.
Once that phase progresses, the construction of Cóndor Cliff will continue, which constitutes the second plant of the complex and the largest.
The reactivation will allow for the recovery of an energy project that had been stalled for years and now has financing and an execution scheme agreed upon between the national government, the construction company, and provincial authorities.