Yacyretá began the electromechanical assembly of Aña Cuá and aims to increase energy generation by 10%

Yacyretá began the electromechanical assembly of Aña Cuá and aims to increase energy generation by 10%

The placement of the first component marks a new stage in the construction of the hydroelectric power plant

Share:

The Binational Entity Yacyretá (EBY) installed the first fixed embedded piece of the suction tube of turbine No. 1 at the Aña Cuá hydroelectric power plant.

The component, weighing approximately 32 tons, was manufactured by the German company Voith and marks the beginning of the electromechanical assembly of the project, which will feature three turbines and will increase energy generation by 10% at Yacyretá.

The play.
The play.

This advancement represents a fundamental step for the development of the infrastructure that will allow for the utilization of a greater amount of water resources and expand the energy production capacity of the complex.

The installation required a highly complex technical operation, involving engineers, technicians, and workers from the Binational Entity Yacyretá. The work of the specialized teams was crucial to successfully place a structure of this size.

The play.
The play.

Aña Cuá: an expansion to generate more energy

The project was designed to take advantage of the ecological flow currently circulating through the Aña Cuá arm, without the need to modify the main reservoir of Yacyretá. This flow is maintained to preserve the flora, fish fauna, and the rest of the ecosystem associated with the watercourse.

With this infrastructure, the initiative aims to increase electricity generation by utilizing available water resources, incorporating new production capacity without altering the conditions of the existing reservoir.

The expansion began to take shape after years of a series of feasibility studies and designs aimed at improving the hydroelectric utilization of Yacyretá and optimizing the available energy. The development included various stages of planning, awards, and socio-environmental monitoring, until reaching the current progress of the project.

The play.
The play.

A strategic project for Argentina and Paraguay

The mechanization of the Aña Cuá arm constitutes one of the most important energy infrastructure projects in the region in recent decades. Its development involves Argentina and Paraguay and aims to strengthen electricity generation capacity.

With the installation of the first electromechanical piece, construction enters a key stage for the future commissioning of the three turbines. The upcoming advancements will be related to the incorporation of the components that will integrate the generation system.

The expansion will deepen the hydroelectric utilization of the binational complex and add 10% of energy generation to the current capacity of Yacyretá, with the goal of strengthening electrical infrastructure and the use of available water resources.